Planned Works Calendar

Listed below you can find all the main works scheduled at the EUI Campus from Monday 4 July until Sunday 21 August: 

 

Badia Fiesolana Laundry Area


  • From Monday 4 July until Sunday 17 July building works (noisy);
  • From Monday 4 July until Friday 15 July network cabling works (not noisy);
  • From Monday 18 July until Friday 22 July electrical and mechanical works (not noisy).

Badia Fiesolana Mansarda


  • From Monday 18 July until Wednesday 20 July building works (noisy)
  • From Thursday 21 July until Tuesday 26 July electrical works (not noisy).

Badia Fiesolana Control room and bank corridor (restrooms)


  • From Monday 18 July until Saturday 20 August building works (noisy)

Badia Fiesolana Library (restrooms Vasco de Gama side, entrance floor and upper floor)


From Monday 1 August until Saturday 20 August building works (noisy)

Badia Fiesolana Archivium


  • From Monday 4 July until Friday 8 July building works (noisy)
  • From Monday 11 July until Wednesday 13 July electrical works (not noisy)
  • From Thursday 21 July until Friday 22 July carpentry works (not noisy).

Badia Fiesolana Theatre and SPS Department (restrooms)


  • From Monday 18 July until Saturday 20 August building works (noisy between 6 am and 9.30 am).

Convento San Domenico


  • From Monday 4 July until Friday 29 July building and electrical works (not noisy). 

Villa Raimondi


  • From Monday 18 July until Friday 29 July building works in the green area (not noisy).