According to the priority list sent by ECO, on top of the agenda was sound insulation of some rooms, which has already been carried out. Lights will follow right after that.
Update of 15/05/2018: REFS has already obtained an overall quotation for the improvement of the lighting system, which will be included in the request of additional funding for extra works planned for June 2018.
Update of 12/10/2018: there is a budget problem, REFS will try to plan the intervention on 2019 funds.
Page last updated on 09 November 2018